Geisinger Multi-Specialty Clinic

Scranton, PA

Healthcare Construction

Sordoni served as Construction Manager for this interior renovation for Geisinger Health System, transforming an existing one‑story space into new clinical areas, including pressure‑monitored procedure rooms, exam rooms, PFT testing rooms, and oxygen storage.

The project included full interior demolition and complete installation of new finishes, casework, plumbing and electrical fixtures, and a new fire alarm system. Mechanical upgrades involved new systems, ductwork, fans, and grilles, along with an expanded IDF room to support additional data racks and cabling. Work also required saw‑cutting the existing slab to install new underground sanitary lines before placing new concrete floors.

Despite an initially planned 13‑week schedule, Geisinger requested accelerated completion in just 9 weeks. Sordoni met the challenge and delivered on time. Working adjacent to active healthcare operations, the team implemented strict infection control measures, including daily‑inspected ICRA barriers and carefully planned debris removal routed directly to outdoor dumpsters to avoid disrupting occupied areas.

Privacy Preferences

When you visit our website, it may store information through your browser from specific services, usually in the form of cookies. Here you can change your Privacy preferences. It is worth noting that blocking some types of cookies may impact your experience on our website and the services we are able to offer.

Click to enable/disable Google Analytics tracking code.
Click to enable/disable Google Fonts.
Click to enable/disable Google Maps.
Click to enable/disable video embeds.
Our website uses cookies, mainly from 3rd party services. Define your Privacy Preferences and/or agree to our use of cookies.